MONADNOCK REGIONAL SCHOOL BOARD
FACILITIES COMMITTEE
Unapproved
Minutes for the Meeting of
The Facilities Committee met at
1. Approval of the
minutes for the meeting of
Motion to approve by B. Smith; seconded by G. White. VOTE: 3 0 0 3
2. Approval of the
minutes for the meeting of
Motion to approve by G. White; seconded by B. Smith. VOTE: 3 0 0 3
3. Public Comments: None
4. Kaestle-Boos Associates, Inc.
Presentation by David King, Jennifer Mangiagli and Wayne Whippie
Passed out new Site Plan page for proposed Middle School with the following
additions….
- limits of flood lines
- layout/limit of septic system for
- location of area proposed and approximate size of proposed septic system for
the Middle School (assuming site is OK)
- set back line for wetlands
Passed out Middle School narrative with revised page 4.1-5; now includes
Construction Cost ($125,000) for Middle School leach field; this is not a new item
as it had been “included” in the original estimates
Discussed making
45 copies of Facilities Study – will use printer in
because they are less expensive
Passed out revised copy of “Estimate Comparison”….
- changed the Construction estimates/sf to
(1) Additions & Renovations – grades 7-12, 4/10 - $173.93/sf
(2) New Construction – grades 7-12, 4/10 - $242.94/sf
- added new line: Reimbursement Targets (at 57%)
Passed out “Priority List for Site, Architectural, Plumbing, Mechanical and Electrical”
(dated
- in attempt to answer the $5,000,000 question
- List of “recommended” work in order to continue to use the existing MRHS/MS
page 2 –
facility in lieu of completing a comprehensive addition and renovation project
- total of items listed = approximately $9,000,000 (and some things have
not yet been estimated)
- emphasis on NEASC recommendations, fire safety codes, State codes, other
safety codes, site issues,
- Note: These are not new estimates; these figures were included in original
estimates from Kaestle-Boos.
- In David King’s opinion….the most critical items are A-1 thru A-10 (Remedia-
tion of Building Codes, Fire Codes, and Life Safety items; also, remediation
of NH DOE Conditional Approval Requirements (see p. 7.2-5)
- comment concerning science labs – if we “reduced” the number of students in
each class we could meet the State requirement of 60sq ft/student.
- p. 7.2-5 = Remediation of NEASC concerns
- p. 7.2-6 = Handicapped accessibility items
- p. 7.2-11 = Plumbing, mechanical and electrical recommendations
- Total for all of this is $7,698,500, and it doesn’t include cost of taking down
ceilings and items not yet estimated.
(C.
Dreyfuss arrives
- Discussed summary of recommendations on pages 7.2-14 & 15
(1) Cost of core infrastructure = $5,326,000
(2) It was suggested that we might want to do “all” systems in regions of
the building, one at a time; would be less expensive
- David King stated that work that “should” be done will cost more than
$5,000,000; also, if we limit ourselves to spending only $5,000,000 we
might not get State reimbursement as some of the work wouldn’t be eligible
for reimbursement; also, work couldn’t be done just in Summer
- Kaestle-Boos will provide an additional summary for the Facilities meeting
on July 9th.
doesn’t think codes need to apply. David King responded politely……….
- There are two major codes: Fire Safety Codes (received from fire marshal)
and Building Codes (received from building officials); and there are also
the building accessibility codes
- If the fire
to comply – it will not be grandfathered
- the State fire marshal is now required to inspect all public buildings in the
State; we don’t know when they’ll get around to us
- David King: “Once you start, you may not be able to stop.”
5. Auditorium Seats
Brett received four bids…..
$72,500 C B Seating (incl 5-year warranty)
$83,000
page 3 –
$76,820 Robert Lord
$120,802 Criteria
B. Smith moved acceptance of bid from C B Seating; seconded by C. Dreyfuss. (Plus contingency to bring total up to the original approved motion of up to $85,000.00)
VOTE: 4 0 0 2
We discussed color options.
We discussed salvage of existing seats; B. Smith will coordinate these arrangements
6. Asbestos Abatement
–
Brett received three bids……
$12,925.00 - Catamount
$13,840.00 - Dec-Tam
No Bid - A-Best Abatement
Motion to accept Catamount bid with a 10% contingency (Total: $14, 217.50) by
C. Dreyfuss; seconded by B. Smith. VOTE: 4 0 0 2
7. Updates
- B. Beliveau stated that everything that has been approved is moving right along;
S & S
Painting will start on gym ceiling on
removed around
- There was a brief discussion as to whether we should save pieces of the gym
floor for a fund raiser (Celtics played on it when it was fairly new)
8. Report: Bill Mitchell
- Homestead Woolen
Mills has offered to let us tie-in
chip furnace they plan to install; would be piped under the street to Cutler.
- Troy Fire Dept. wants to put in transfer
switch at
use school as an emergency shelter; they’d install an emergency generator
- Problem: T. Walsh is putting in a new walk-in freezer outside kitchen at
- Passed out copy of Health Office layout and response from NEASC
- Need repairs to domestic hot water tank in high school
9. Statement for Policy Committee
B. Mitchell recommended the following…….
- Strategic planning for facilities(including CIP)
- Oversight of facilities and grounds.
The next meeting will be on July 9th at 7:pm in the library at the high school.
The meeting was adjourned at
Respectfully submitted,
Gene White